City Plans And Projects

Project Name  Current Status % Complete
Northside Study/
Housing Study
Second Community Plan held on 8/27/18.  90%
Old Mill Site
Clean Up
Phase I ESA
Phase II ESA
Phase II is complete, information submitted to EPD
80%
Facilities Assessment Study  30 of 30 facility assessments are complete. Staffing assessment contract under review.
100%
Maintenance & Sanitation Admin Building Currently on hold. N/A
City Hall Renovations Plumbing in downstairs breakroom complete. Flooring complete with one exception upstairs breakroom. 
Interior 80%
Exterior Roofing & Painting 100%
Old Jail/Downtown
Master Plan
Phase 1 Complete,
Awaiting Proposal for Phase 2
Environmental Studies:  50% complete
Parks Master Plan Complete  100%
Maintenance Facility at Hunter Park Project has been cancelled. N/A
Pay and Compensation (Evergreen) Study Complete. 100%
Fleet Study  Faster software will go live by April 2019.
100%
City Branding Study Complete. Branding guide submitted to City. 100%
Mill Village/Willing Workers Park Renovations Bid Awarded to GMC. Initial planning phase. 3%
Hawthorne Center Restroom Renovations Project will be performed “in-house”.  Scheduled to begin mid-January 2019. N/A
Unified Development Code Rewrite Deadline for draft from Jacobs is February 1. 75%
Douglasville Comprehensive Plan Update Public hearing held on 8/30/18. 90%, must be complete by October 31
 Windshield Study Old Mill Village and Downtown area  37%
 Riverside Parkway Bridge Rehab  Preliminary Engineering Complete  25%
 Dallas Highway (SR 92) LCI Study ADP hired as a consultant 10%
 
Colquitt Terrace
Construction is in progress.  Constructiion - 20%
 PD Community Center Parking Lot Construction is substantially complete. Final punch list is in progress to close out the project.  95%
 SPLOST Resurfacing Bid Package Short list of streets for final SPLOST batch has been approved by Council. This will be bid in early 2019.  Design - 100%
 SPLOST Proposed Project List and Schedules

List of remaining projects in the SPLOST program turned in for review. 90% 
 Douglas Boulevard Enhancements  Preliminary design is in progress  Preliminary Design - 5%
 I-20 @ SR 92 Interchange Enhancements Preliminary design is in progress; GDOT encroachment permit has been submitted. Design -
50%
 Lighting & Banners Phase II Curb and Gutter    5%
 SR92/Dallas Hwy and Fairburn Road Enhancements   Conceptual design is in progress. Concept design - 10% 
 Cedar Mountain Road Permitting Process – Waiting on Land Disturbance Project    
 West Court House Square  TBA  
 Club Drive Project  TBA  

 SPLOST 172x114
SPLOST Projects
 DOUGLASVILLE_MPLAN_172x114
Downtown Master Plan &
10 Year Strategic Plan


Chandler Thinks logo 172x114
Douglasville Branding Study
AE Comm logo p1191
Douglasville SPLOST Update
SR 92 at CVS for p1191
State Route 92 Project
 
Comp Plan 071918 gfx172x114 
City/County Comprehensive Plan

Goals and Objectives on 1191
Goals and Ojectives