City Plans And Projects

Project Name  Current Status % Complete
Northside Study/
Housing Study
Second Community Plan held on 8/27/18.  90%
Old Mill Site
Clean Up
Phase I ESA
Phase II ESA
Phase II is complete, information submitted to EPD
80%
Facilities Assessment Study  30 of 30 facility assessments are complete. Staffing assessment contract under review.
70%
Maintenance & Sanitation Admin Building Currently on hold. N/A
City Hall Renovations Plumbing in downstairs breakroom complete. Flooring complete with one exception upstairs breakroom. 
Painting 100%
Roof & Painting 80%
Old Jail/Downtown
Master Plan
Phase 1 Complete,
Awaiting Proposal for Phase 2
Environmental Studies:  50% complete
Parks Master Plan Complete  100%
Maintenance Facility at Hunter Park Currently on hold. N/A
Pay and Compensation (Evergreen) Study Complete. 100%
Fleet Study  Legal reviewing contract for Fleet Consultant 
35%
City Branding Study Complete. Branding guide submitted to City. 100%
Mill Village/Willing Workers Park Renovations RFP for design and construction scheduled to be opened Sept 20th. Advertised to the public on Sept. 6 30%
Jesse Davis Restroom Renovations 100% documents and bid packet received from architects. RFP ready for advertising.  30%
Unified Development Code Rewrite Meetings held include Steering Committee Sept. 18th and technical committee meeting Sept. 26th 75%
Douglasville Comprehensive Plan Update Public hearing held on 8/30/18. 90%, must be complete by October 31
 Windshield Study Old Mill Village and Downtown area  30%
 Riverside Parkway Bridge Rehab  Preliminary Engineering Complete  25%
 Dallas Highway (SR 92) LCI Study ADP hired as a consultant 10%
 
Colquitt Terrace
Waiting on final approval from WSA.
GA Power has already relocated
 Constructiion - 5%
 PD Community Center Parking Lot Parking lot has been paved and striped. Contractor awaiting approved change order to procure lighting fixtures  75%
 SPLOST Resurfacing Bid Package Short list of streets for final SPLOST batch has been approved by Council. This will be bid in early 2019.  Design - 100%
 SPLOST Proposed Project List and Schedules

List of remaining projects in the SPLOST program turned in for review. 90% 
 Douglas Boulevard Enhancements  Conceptual design is in progress  Concept Design - 90%
 I-20 @ SR 92 Interchange Enhancements  Preliminary design is in progress Preliminary design
20%
 Lighting & Banners Phase II Curb and Gutter    5%

 SPLOST 172x114
SPLOST Projects
 DOUGLASVILLE_MPLAN_172x114
Downtown Master Plan &
10 Year Strategic Plan


Chandler Thinks logo 172x114
Douglasville Branding Study
AE Comm logo p1191
Douglasville SPLOST Update
SR 92 at CVS for p1191
State Route 92 Project
 
Comp Plan 071918 gfx172x114 
City/County Comprehensive Plan

Goals and Objectives on 1191
Goals and Ojectives